Sr. No |
Activity |
Responsibility |
---|---|---|
01. | Submission of application by consumer on online portal along with Rs. 500/- processing fees | Consumer |
02. | Acknowledgement of application by DISCOM | DISCOM |
03. | Site verfication/ technical feasibility/ estimate by empaneled vendor of the choice of the consumer and submission of the same to DISCOM by the vendor |
Empaneled Vendor |
04. | Letter of Approval (LoA), approval of estimate and approved Central Financial Assistance (CFA), if eligible. Aadhar seeding of the beneficiary and handing over/mailing of Meter Agreement form to consumer |
DISCOM |
05. | Execution of Meter Agreement | DISCOM & Consumer |
06. | Payment of 50% of balance amount payable by consumer to DISCOM | Consumer |
07. | Installation of rooftop solar system, submit work completion report/ certificate and intimation of meter procurement intimation |
Empaneled Vendor |
08. | Inspection by DISCOM, installation of meter and commissioning and synchronization of the system with grid | DISCOM |
09. | Release of balance 50% payment by consumer to vendor | Consumer |
10. | Release of CFA and full payment to vendor by the DICSOM | DICSOM |
11. | Billing Process | DICSOM |