Responsibilities


Sr. No
Activity
Responsibility
01. Submission of application by consumer on online portal along with Rs. 500/- processing fees Consumer
02. Acknowledgement of application by DISCOM DISCOM
03. Site verfication/ technical feasibility/ estimate by empaneled vendor of the choice of the consumer and submission of the
same to DISCOM by the vendor
Empaneled Vendor
04. Letter of Approval (LoA), approval of estimate and approved Central Financial Assistance (CFA), if eligible.
Aadhar seeding of the beneficiary and handing over/mailing of Meter Agreement form to consumer
DISCOM
05. Execution of Meter Agreement DISCOM & Consumer
06. Payment of 50% of balance amount payable by consumer to DISCOM Consumer
07. Installation of rooftop solar system, submit work completion report/ certificate and intimation of meter
procurement intimation
Empaneled Vendor
08. Inspection by DISCOM, installation of meter and commissioning and synchronization of the system with grid DISCOM
09. Release of balance 50% payment by consumer to vendor Consumer
10. Release of CFA and full payment to vendor by the DICSOM DICSOM
11. Billing Process DICSOM